Can the City of Ottawa make me sod the lot after a demolition?

Question

Can the City of Ottawa make me sod the lot after a demolition?

Answer from Demolition IQ

Demolition Control By-law 2012-377 gives the City a direct path to require sodding. Under section 8, if you demolish a residential property inside the Area of Demolition Control and no building permit for a replacement structure has been issued, the General Manager may issue the demolition control permit with conditions. Those conditions can include that the lot be graded, sodded, seeded and landscaped, that no interim use of the lot occur, and that a registered agreement be entered into. The Ward Councillor must also agree before the permit issues on those terms.

That condition applies specifically to properties inside the demolition control area. Whether your property falls inside it depends on the Schedule 1 map attached to the by-law, which is an image. Ask the City whether the address is inside the Area of Demolition Control before you plan the project.

Two other points narrow when this matters. First, the demolition control permit requirement applies to residential properties as the by-law defines them. Accessory buildings, meaning detached garages and sheds, are excluded from that definition, so taking down a garage or shed does not trigger demolition control. Second, if a building permit for a replacement building is already in hand when you apply, the Chief Building Official shall issue the demolition control permit.

Outside the demolition control area, we did not find a City rule that requires a homeowner to sod or seed a lot after a residential demolition. The Building By-law 2014-220 requires the permit holder to give notice within two days of completing the demolition, and the site fence must come down within 30 days of completion, but neither provision mentions landscaping.

The practical step from here is to confirm with the City's Building Code Services whether the property is inside the demolition control area, and if it is, whether a building permit for the replacement will be in place before you apply for the demolition permit.

Ottawa Demolition Contractors

Want this done at your place?

Tell us what you are taking down and we'll send it to local Ottawa demolition contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.

Fields marked are required.

We won't call you. There's no phone box above because we don't ask for one — your estimate comes by email, on your time.

Request received We’ve sent your details to local Ottawa demolition contractors. Interested contractors reply by email. A confirmation is on its way to your inbox.

Demolition IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.

Ready to Get Quotes?

Find local demolition contractors in Ottawa. Free matching, no obligation.

Find a Demolition Contractor