Do I need a permit to demolish a house or garage in Ottawa?
Yes for a house. The City of Ottawa says "You need to obtain a building permit to relocate or demolish an existing building or structure." Its demolition page names two exemptions: "certain building types (silos, and barns)" and non-load-bearing interior partitions. A detached garage is a building, so plan on a permit; for a small shed the page gives no size threshold, so ask the City's Building Code Services before taking it down.
Does stripping a room to the studs need a demolition permit?
Removing non-load-bearing interior partitions does not need a demolition permit, according to the City. The City says nothing either way about stripping finishes such as drywall, cabinets and flooring, so ask Building Code Services about your job. A load-bearing wall is structural work, and the renovation that follows a strip-out may need a building permit of its own.
How long does the City take to review a demolition permit?
The City lists "First review - 10 business days". An inspection is required when demolition starts and is booked 48 hours ahead, and the permit holder tells the City within two days of finishing. Plan the utility sign-offs alongside it: Enbridge needs 44 days from payment to disconnect gas.
Fees & Prices
What is the City's fee for a demolition permit in 2026?
The 2026 fee schedule lists a Permit to Demolish at $117 for the first 5,000 square feet of gross floor area, plus $12.75 for each additional 1,000 square feet, and notes that a sewer disconnection fee may apply. The $1,170 and $3,510 figures on the same schedule are surcharges for starting a demolition before the permit is issued on a demolition-control or designated heritage property, not the permit fee.
What do published guides say a house demolition costs?
The published prices seen October 2026 (Ontario, GTA and Canada; we found no Ottawa-specific published price) put a typical house at about $15,000 to $40,000, or about $5 to $10 per square foot. Those figures take the house down; removing the basement and foundation below grade and backfilling the hole are excavation work and are priced separately. Compare written quotes for the same scope.
What do strip-outs and garage removals cost?
The published prices seen October 2026 (Ontario, GTA and Canada; we found no Ottawa-specific published price) put a kitchen strip-out at about $1,500 to $5,000, a bathroom at about $1,000 to $4,000, a full gut to the studs at about $12 to $25 per square foot, and a wood-frame detached garage at about $3,000 to $8,000. We found no shed or deck removal price from two independent sources.
Utilities
Which utilities must sign off before an Ottawa demolition?
The City's Demolition Permit Clearances Form has sign-off boxes for City water and sewer, septic decommissioning where there is one, Bell, Rogers, Enbridge Gas, Hydro Ottawa, Hydro One, and an emptied heating-oil tank. The owner also certifies the premises "are free of rodents". The form says "Fees may be levied by each utility".
How far ahead do I need to call Enbridge?
The City's clearances form says "Enbridge Gas Distribution requires 44 days from time-of-payment to disconnect natural gas service." It is the longest published wait in a demolition, so arrange it before anything else.
Does Hydro Ottawa charge to remove the electrical service?
Hydro Ottawa's Conditions of Service say permanent removal of a 120/240 V service of 200 A or less for a residential single family or duplex home is provided free of charge at the homeowner's request. Other removals are charged on a cost-recovery basis.
Asbestos & Site Safety
Do I need an asbestos test before demolition?
Health Canada advises hiring a professional to test for asbestos before renovating or demolishing, and says asbestos was mainly used in buildings and homes before 1990. The City's demolition page says a project owner must identify designated substances and give the list to prospective contractors before contracting, under section 30 of the Occupational Health and Safety Act. If asbestos is found, its removal is a job for an asbestos abatement contractor.
Does a demolition site need a fence?
The City's Building By-law requires a fence around the site before demolition: 1.8 m high if the building is 3.0 m or less from a public way, or 1.2 m for a residential building of up to three storeys set farther back. Gates are locked when the site is unattended. Work entirely inside an existing structure, with entry limited, is exempt.
What hours can demolition equipment run in Ottawa?
The Noise By-law bans construction equipment between 10 pm and 7 am, and before 9 am on Sundays and holidays. For demolition and infill projects, the City's 3-1-1 page lists stricter hours: no work between 8 pm and 7 am on weekdays, or between 7 pm and 9 am on Saturdays, Sundays and holidays.
Heritage & Demolition Control
What is demolition control in Ottawa?
The Demolition Control By-law covers residential property inside an area mapped on its Schedule 1. Demolishing a home there needs a demolition control permit, and the City issues it once a replacement building permit has been issued. Without one, conditions such as grading and sodding the lot can apply. Garages and sheds are not covered: the by-law's definition excludes "a subordinate or accessory building".
Can I demolish a heritage property?
Not without approval. Under the Ontario Heritage Act, a designated property needs council consent to demolish, and a property in a heritage conservation district needs a municipal permit. A property that is listed but not designated needs at least 60 days' written notice to council before demolition.
Does a demolition permit let me remove trees?
No. The City says other approvals, including a demolition permit, "do not in themselves convey permission to remove trees". Where tree removal is part of a demolition, or work is planned within the critical root zone of a protected tree, a full Tree Information Report is required.
Hiring & Contracts
Do demolition contractors need a licence in Ontario?
We found no demolition-contractor licence in Ontario's trade rules or the City's business licence list. Ask for a WSIB clearance certificate and proof of liability insurance, and check them yourself. This site does not license, screen or verify contractors.
What happens to the debris?
The City says demolition and building waste is not collected with regular garbage and goes to the Trail Road landfill or another landfill. The landfill does not accept asbestos, and it does not accept commercial garbage, so ask each contractor where their load goes and whether hauling is in the price.
Can I cancel a demolition contract after signing?
Under Ontario's Consumer Protection Act, a direct agreement, one made in person away from the contractor's place of business, can be cancelled for any reason until 10 days after you receive the written copy. The same Act says the final price cannot be more than 10 per cent over an estimate.
Have a different question?
Get answers about demolition permits, utilities, asbestos testing, costs and hiring in Ottawa from Demolition IQ.
Ready to Get Quotes?
Get matched with a local demolition contractor in Ottawa. Free, no obligation.