My Ottawa demolition estimate went up at the end. Is there a limit?
My Ottawa demolition estimate went up at the end. Is there a limit?
Ontario's Consumer Protection Act, 2002 sets a hard limit: where a consumer agreement includes an estimate, the supplier shall not charge an amount that exceeds the estimate by more than 10 per cent.
That rule applies to any consumer agreement that includes an estimate. It does not require a separate written consent, a signed acknowledgment, or any other condition before it kicks in. If the contractor gave you a number and called it an estimate, that rule already applies. The Act also requires a direct agreement, one negotiated at your home rather than at the contractor's place of business, to be in writing and delivered to you, and you may cancel it without reason from the day you enter into it until 10 days after you receive the written copy.
A few things are worth checking in what you were given. The Construction Act also requires each payer to hold back 10 per cent of the price of services and materials as they are supplied; ask a lawyer how that holdback interacts with your payment schedule.
What to check before you respond to the contractor:
- Does the agreement use the word "estimate", "quote" or "fixed price", and is the total figure clearly stated?
- Is the reason for the increase identified in writing, and does the increase exceed 10 per cent of the original figure?
- Is the payment schedule written into the agreement, and does it match what you were told?
Want this done at your place?
Tell us what you are taking down and we'll send it to local Ottawa demolition contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.
Demolition IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.