Building By-law 2014-220 gives a clear deadline: the site fence must come down no more than 30 days after the demolition is complete.

The same by-law sets out when the fence has to go up in the first place. If the building is 3.0 m or less from a public way, the fence must be 1.8 m high. If a residential building of up to three storeys sits more than 3.0 m from a public way, a 1.2 m fence is required. Gates stay locked whenever the site is unattended. The fence requirement does not apply where all the demolition is contained within an existing structure and entry to the structure is limited, or where the hazard to the public is minimal.

The 30-day removal deadline runs from completion of the demolition, not from the date the permit was issued or the date work started. The by-law also requires the permit holder to give the City notice within two days of completion, so that notice and the fence removal are both tied to the same completion date.

One related timing point: the City requires an inspection at the commencement of demolition, booked 48 hours in advance. That inspection is separate from the fence deadline, but it is worth confirming both dates are in your contractor's plan before work starts.

Make sure the contract states in writing who is responsible for erecting the fence, who removes it, and that removal will happen within the 30-day window the by-law requires.

Ottawa Demolition Contractors

Want this done at your place?

Tell us what you are taking down and we'll send it to local Ottawa demolition contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.

Fields marked are required.

We won't call you. There's no phone box above because we don't ask for one — your estimate comes by email, on your time.

Request received We’ve sent your details to local Ottawa demolition contractors. Interested contractors reply by email. A confirmation is on its way to your inbox.

Demolition IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.

Ready to Get Quotes?

Find local demolition contractors in Ottawa. Free matching, no obligation.

Find a Demolition Contractor