When does the City of Ottawa inspect a demolition, and how is it booked?
When does the City of Ottawa inspect a demolition, and how is it booked?
An inspection is required when demolition starts, and it is booked 48 hours in advance, according to the City of Ottawa. After the work is finished, the permit holder must give the City notice within two days of completion, under Building By-law 2014-220 s.29.
Those are the two time figures the City's demolition page and Building By-law give for this stage.
Booking the inspection
The City's guidelines say a My ServiceOttawa account is used to submit and manage permit applications and to request inspections. The permit holder is responsible for both bookings: the 48-hour advance request for the commencement inspection, and the notice within two days of completing the demolition.
A few things follow from this that are worth confirming with whoever holds the permit. The Building By-law allows a contractor to apply as the owner's authorized agent, so ask whether the contractor or the homeowner will be listed as permit holder, because that determines who is responsible for booking the inspection and filing the completion notice. If the contractor holds the permit, ask how they will confirm to you that both have been done and on what dates.
The permit application itself goes through a first review in about 10 business days, according to the City's demolition page.
Before signing, ask who will book the inspection and who will file the completion notice, and get the answer in the contract.
Want this done at your place?
Tell us what you are taking down and we'll send it to local Ottawa demolition contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.
Demolition IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.
Ready to Get Quotes?
Find local demolition contractors in Ottawa. Free matching, no obligation.