What goes into a demolition permit application in Ottawa?

Question

What goes into a demolition permit application in Ottawa?

Answer from Demolition IQ

A demolition permit application in Ottawa is filed online through a My ServiceOttawa account. The application has four main pieces: the completed permit application form, the fee, a current plan or survey with full dimensions, and the Demolition Permit Clearances Form signed off by each utility and authority connected to the property.

What the clearances form covers

The clearances form holds the longest published wait in the job. Each utility connected to the property signs it:

  • City water (disconnect water utility)
  • City sewer (disconnect sewer utility)
  • Enbridge Gas, which requires 44 days from time of payment to disconnect natural gas service
  • Hydro Ottawa or Hydro One (ask which one serves the property)
  • Bell Canada and Rogers
  • The Rideau Valley Conservation Authority's Ottawa Septic System Office, if there is a septic system
  • Confirmation that any heating oil tank has been emptied
Because Enbridge Gas takes 44 days from payment, that arrangement needs to be made well before the permit application is complete.

The Demolition Review Form is also part of the package. It asks four questions: whether the building is more than three storeys; whether the footprint exceeds 600 square metres; whether demolition will go below the footing of an adjacent building; and whether explosives or lasers will be used. A yes to any of those means the applicant must also submit a demolition brief and retain a Professional Engineer for general review.

The 2026 permit fee is $117 for the first 5,000 square feet of gross floor area, plus $12.75 for each additional 1,000 square feet. A sewer disconnection fee may also apply; the City's fee schedule notes it but we did not find the amount.

The City's published first review time is 10 business days. An inspection is required at the start of demolition, booked 48 hours in advance, and the permit holder must give the City notice within two days of completing the work.

The designated substances list is a separate step: ask each contractor how they handle it before you sign with one.

Before work starts, make sure the written contract sets out exactly what comes down, where the work stops, who applies for the permit and who arranges each utility sign-off, where the debris goes, and the full payment schedule with dates.

Ottawa Demolition Contractors

Want this done at your place?

Tell us what you are taking down and we'll send it to local Ottawa demolition contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.

Fields marked are required.

We won't call you. There's no phone box above because we don't ask for one — your estimate comes by email, on your time.

Request received We’ve sent your details to local Ottawa demolition contractors. Interested contractors reply by email. A confirmation is on its way to your inbox.

Demolition IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.