Can the gas line to a detached garage in Orleans stay live during demolition?

Question

Can the gas line to a detached garage in Orleans stay live during demolition?

Answer from Demolition IQ

No, the gas line cannot stay live. Ontario's construction regulation, O. Reg. 213/91 s.214(3), states that all gas, electrical and other services that may endanger persons who have access to a building or structure shall be shut off and disconnected before, and shall remain shut off and disconnected during, the demolition.

That rule binds the constructor, meaning the contractor doing the work. It is not a matter of preference or timing: the line must be off and physically disconnected before demolition begins.

The practical constraint is Enbridge Gas. The City's Demolition Permit Clearances Form requires Enbridge to sign off before the City issues the permit, and Enbridge Gas Distribution requires 44 days from time-of-payment to disconnect natural gas service. That is the longest wait in the process for any utility on the form, so contacting Enbridge and making payment is the first utility step to take after you decide to proceed. We did not find a published disconnection fee from Enbridge; ask them directly what they charge.

A few other points specific to a garage demolition:

  • The clearances form also has sign-off boxes for Hydro Ottawa or Hydro One (ask which one serves the garage), Bell Canada and Rogers if any lines run to the structure, and the City's water and sewer utilities if the garage has a drain or water supply.
  • The oil tank "Home Heating Fuel" box on the form applies if the garage has a fuel-fired heater with a tank; the owner certifies the tank has been emptied.
  • O. Reg. 213/91 s.214(4) also requires that toxic, flammable or explosive substances be removed before demolition begins. Ask how any stored fuel will be removed.
The clearances form is the owner's responsibility: the City's guidelines state that it is the responsibility of the owner to contact the utility provider for each and every utility connected to the property. Before signing a demolition contract, confirm in writing which party, you or the contractor, will contact each utility, make each payment and collect each signed clearance, because the permit application cannot proceed until the form is complete.
Ottawa Demolition Contractors

Want this done at your place?

Tell us what you are taking down and we'll send it to local Ottawa demolition contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.

Fields marked are required.

We won't call you. There's no phone box above because we don't ask for one — your estimate comes by email, on your time.

Request received We’ve sent your details to local Ottawa demolition contractors. Interested contractors reply by email. A confirmation is on its way to your inbox.

Demolition IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.

Ready to Get Quotes?

Find local demolition contractors in Ottawa. Free matching, no obligation.

Find a Demolition Contractor